"SEND THE STUDENTS HOME!"
THE SCHOOL BUILDING HAS FAILED!

It seems that the Hurricane, Utah, School Board was faced with a problem. A portion of their elementary school was constructed on improperly compacted fill material. Three classrooms were showing perimeter settlement of up to two and one-half inches. Two of the partition walls between classrooms also required restoration. Could the building be saved without ruining the budget?

School Building

Atlas Piers of Utah, Inc. installed 14 Atlas Resistance Piers along the perimeter of the foundation and eight piers inside the structure. Not only did the Atlas Resistance Piers provide stabilization, the piers were used to raise the foundation as much as 2-1/2 inches to restore the school to near original elevation.

The Hurricane School Board selected Atlas Resistance Piers to repair the settlement. Twenty-two Atlas AP2S-3500 Piers were used on the perimeter and along the distressed interior partition walls to stabilize and restore the building. The economical and permanent solution to this settlement was accomplished in a matter of days, not weeks. The piers were installed with clean and quiet portable hydraulic equipment. Each pier was tested to a load greater than required to support the structure, thus insuring a factor of safety against future settlement! After lifting the structure, the voids were filled with grout.

THE SOLUTION: ATLAS RESISTANCE PIERS!
"PASSED THE TEST!"

PROJECT SUMMARY
Installed By: Atlas Piers of Utah, Inc.
Number of Piers: 14 exterior, 8 interior
Part Number: AP2S-3500
Avg. Pier Depth: 70 feet - 9 in.
Avg. Load per Pier: 35,866 lbs., exterior
23,175 lbs., interior
Avg. Drive Force: 58,545 lbs., exterior
34,507 lbs., interior
Ultimate Capacity: 85,000 pounds
Amount to Lift: 1/64" to 2-1/2"
Factor of Safety: 1.63 : 1 (Drive to Lift)
(Exterior Averages) 2.37 :1 (Ultimate to Lift)
Factor of Safety: 1.49 : 1 (Drive to Lift)
(Interior Averages) 3.67 :1 (Ultimate to Lift)



Atlas Resistance Piers
Lift Force vs. Drive Force & Ultimate
Graph

The chart above shows how the pier load relates to the "proof load" or driving force and to the ultimate capacity of the pier.

Atlas Resistance Piers Installation        Atlas Resistance Piers Installation

The photograph on the left shows Atlas Resistance Piers being installed along one of the partition walls. The piers are driven to a load bearing stratum or rock by quiet hydraulic equipment.

On the right is a view of an installed Atlas Resistance Pier on the exterior following the successful restoration of the foundation.

Chance Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com