Case Study 110-8
Settlement of Fill Material
During Construction of an
Addition to a Bank
Atlanta, Georgia
Installed By:
Atlas Piers of Atlanta, Inc.
Alpharetta, Georgia
Designed By:
United Consulting Group, LTD
Norcross, Georgia
"MORE THAN INTEREST
RATES ARE DROPPING AT
THIS BANK!"
The site required compacted fill prior to construction of an addition to
the bank. When the contractor noticed cracks appearing in recently installed masonry, soil
tests were ordered along the problem area. The results showed that the compacted fill was
not extended beyond the area of construction.
The construction schedule required that steel framing be installed, but
the structure was showing serious distress. Could the building be saved? Would the
structure have to be demolished and rebuilt? What about the budget and time schedule?

Atlas Piers of
Atlanta installed ATLAS RESISTANCE PIERS along the side and at the back of the bank
addition. Construction continued on schedule saving the customer time and money!
THE
SOLUTION: |
ATLAS RESISTANCE PIERS
STABILIZED AND RESTORED
THE FOUNDATION! |
PROJECT
SUMMARY |
| Installed By: |
Atlas Piers of
Atlanta, Inc. |
| Number of Piers: |
25 |
| Part Number: |
AP2S-3500 |
| Test Pier Depth: |
42 feet |
| Test Pier Load: |
48,925 pounds |
| Driving Force: |
62,175 pounds |
| Ultimate Capacity: |
85,000 pounds |
Factor of Safety:
(Averages) |
1.27 : 1 (Drive to Load)
1.73 : 1 (Ultimate to Lift) |
 |

The general contractor called a meeting with the geotechnical engineer, structural
engineer architect and Atlas Piers of Atlanta. It was decided to install an ATLAS
RESISTANCE PIER as a test pier.
The test pier proved to be successful. The pier was driven to a depth of 42 feet and
tested with a force of 62,175 pounds. The project engineer and geotechnical engineer
checked the test pier for any long term creep. The results showed that no creep was
detected.
At the corner of the structure where settlement occurred, the total dead load, live
load and wind load was estimated to be 50,000 pounds. The engineers determined the proper
pier spacing after calculating loads.
The photograph at the left shows a fracture in the masonry and in the concrete floor.
|
 The photograph at right shows how the
structure is supported and restored using the ATLAS RESISTANCE PIER. The hydraulic hand
pump can be seen on the concrete floor. A manifold directs the pressure to several piers
for gentle and even support of the structure.
Note that an ATLAS RESISTANCE PIER is being installed at the left side of the
photograph. The hydraulic pump and pier installation equipment are visible.
|
ATLAS RESISTANCE PIERS are installed in small excavations using portable
equipment. This photograph was taken from the steel framing as the construction continued.
Each ATLAS RESISTANCE PIER is driven to a load bearing stratum and tested before the
structure is supported. The quiet hydraulic pump is visible to the left of the
technician. The drive stand and hydraulic drive cylinder can be seen to the right of the
technician and adjacent to the structure.

|
SUCCESS!
These photographs show the
masonry fracture before and after the foundation was restored with ATLAS RESISTANCE PIERS.
The crack which measured 3/8 inch was completely closed.



The construction on the bank continued with no interruptions. The general contractor
was able to complete the building on schedule. These photographs show the completed
building.

Chance
Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com
|
|
|