Atlas-Helical &
ATLAS RESISTANCE PIERS

CASE STUDY 110-9

Atlas-Helical Slab Piers and
Atlas Resistance Piers are Used
to Restore and Stabilize a New House

Atlanta, Georgia

Installed by:
Atlas Piers of Atlanta
Alpharetta, Georgia

 

Designed by:
Peach State Building Consultants, Inc.
Lawrenceville, Georgia

 

LOOK OUT! New House Headed South!

Front of the residence

This is a view of the front elevation of the residence. The ATLAS RESISTANCE PIERS
were installed on the rear of the structure and Atlas-Helical Slab Piers inside.

Description of Site: This house is situated on a sloping lot. The cut and fill lot slopes at approximately one foot in five feet. Behind the structure the grade drops to a swale 15 feet below the lot at a slope of 1 to 1. The rear of the structure is constructed upon graded fill. The engineers found evidence of active slope movement of the fill. Standard Penetration Test values indicated values of 2 or less over vertical expanses of 5 feet or more in the area of fill.

Description of Structure: This new two story house has a full basement that is below grade at the front of the house and above grade at the rear. The upper levels of the structure and the rear wall of the basement are of wood frame construction. The front of the house is brick veneer while the rear and sides have siding. The house showed settlement of up to 5 inches with respect to the front of the house. The basement slab and the rear porch footing both show fractured concrete.

Description of Findings: The engineers recommended permanent stabilization and restoration of the foundation and slab. Soils with minimum safe bearing pressures of 5,000 psf were found at depths ranging from 5 to more than 15 feet. ATLAS RESISTANCE PIERS and Atlas-Helical Slab Piers were chosen to support and restore the structure. The recommendation to stabilize the soil mass was the construction of a 6 foot high crib wall and slope modification of the back yard.

Full basement of two story house

 

Technician installing the pier pipe

The photograph above shows the rear of the structure where settlement occurred. ATLAS RESISTANCE PIERS were installed from the air conditioning units to the rear and across the back of the house.

The technician is shown in both photos installing the pier pipe. The system uses a quiet hydraulic pump for a smooth installation that is without vibration.

Each pier is carefully driven to a suitable load bearing stratum. Before the structure is restored, each pier is individually tested to a load greater than the working load required. This verifies a factor of safety against future settlement.

 Hydraulic lifting rams installed on each Pier

After the ATLAS RESISTANCE PIERS are installed to the load bearing stratum, hydraulic lifting rams are installed on each Pier. The rams are gently actuated together through a manifold arrangement. The photograph below shows a lift of over 5 inches.

Atlas Resistance Pier Installed

Atlas Resistance Pier installed

The photograph above show an ATLAS RESISTANCE PIER installed on the side of the structure. The ATLAS RESISTANCE PIER is ideal for installation in tight locations; only a small, hand dug excavation is required. This is Pier location number 14.

Atlas Piers Installation Summary

Design Engineer: Peach State Building Consultants, Inc., Lawrenceville, Georgia
Installed By: Atlas Resistance Piers of Atlanta -- Alpharetta, Georgia
Atlas Resistance Pier Product: AP2S-3500 Two Piece ATLAS RESISTANCE PIER
Number of Resistance Piers: 18
Average Drive Force: 32,700 pounds
Average Lift Force: 14,160 pounds
Average Factor of Safety: 2.30:1 [130% above actual lift force]
Amount of Lift: up to 5 inches
Average Depth: 14’ - 5"

 

Atlas-Helical Installation Summary

Installed By: Atlas Resistance Piers of Atlanta -- Alpharetta, Georgia
Atlas-Helical Foundation Pier Product: AHS-SPSP-SQ150 /8/ x [5’-0"] Screw Activated Slab Pier AHE-SQ150 x [5’-0"] Extension Assembly
Number of Atlas-Helical Slab Piers: 17
Installation Torque: 3,000 ft-lbs
Depth to Design Torque: 10 to 15 feet
Amount of Lift: up to 2 inches

Technicians installing an ATLAS-Helical Slab Pier

The photograph above shows the technicians installing an ATLAS-Helical Slab Pier at
location "P" inside the structure. The pier is installed until the design torque is achieved.

Holes drilled through the concrete slab

Once the ATLAS-Helical Slab Pier is installed to design torque, the Sub-slab support Assembly is installed. The floor is then restored to as close to original elevation as construction permits by applying torque to the Lifting Bolts evenly across the floor. In the photograph at right show ATLAS-Helical Slab Pier locations "F", ‘G", "H", & "J" after restoration.

The photograph at left shows the preparation required ATLAS-Helical Slab Piers installations. Eight inch diameter holes are drilled through the concrete slab. A technician then excavates and prepares the lower side of the slab to receive the Sub-slab Support Assembly. Following this careful preparation, the ATLAS-Helical Slab Pier is installed using a quiet hydraulic torque motor. This is a view of Pier locations "H", "G", "F" & "E".

Sub-slab support Assembly installed

Atlas Piers
INSTALLATION SUMMARY
Pier Installation Log

Pier
Section

Location and Driving force -- pounds

Pier #1 Pier #2 Pier #3 Pier #4 Pier #5 Pier #6 Pier #7 Pier #8 Pier #9
Sect. #1 33,160 33,160 13,264 11,606 8,290 7,461 12,435 8,290 8,290
Sect. #2     23,212 16,580 16,580 13,264 14,922 14,922 8,290
Sect. #3     33,160 24,870 16,580 16,580 19,896 33,160 12,435
Sect. #4       31,502 31,502 33,160 18,238   13,264
Sect. #5             31,502   14,922
Sect. #6                 14,922
Sect.#7                 31,502

   Analysis of Lifting, Driving and Ultimate Force

Factor of Safety

Location Lifting
Force, lb
Driving
Force, lb
Ultimate
Cap. - lb
Working
F.S.
Ultimate
F.S.
Pier #1 12,875 33,160 85,000 2.58 : 1 6.60 : 1
Pier #2 12,875 33,160 85,000 2.58 : 1 6.60 : 1
Pier #3 12,875 33,160 85,000 2.58 : 1 6.60 : 1
Pier #4 14,420 31,502 85,000 2.18 : 1 5.89 : 1
Pier #5 14,420 31,501 85,000 2.18 : 1 5.89 : 1
Pier #6 15,450 33,160 85,000 2.15 : 1 5.50 : 1
Pier #7 15,450 31,502 85,000 2.04 : 1 5.50 : 1
Pier #8 15,450 33,160 85,000 215 : 1 5.50 : 1
Pier #9 15,450 31,502 85,000 2.04 : 1 5.50 : 1

Results

Location Approx.
Lift - in.
Depth to
Bearing
Pier #1 0" 3' - 6"
Pier #2 0" 3' - 6"
Pier #3 0" 10' - 6"
Pier #4 2" 14' - 0"
Pier #5 2" 14' - 0"
Pier #6 3" 14' - 0"
Pier #7 3" 17' - 0"
Pier #8 3" 10' - 6"
Pier #9 3-1/2" 24' - 6

 

Pier
Section

Location and Driving force -- pounds

Pier #10 Pier #11 Pier #12 Pier #13 Pier #14 Pier #15 Pier #16 Pier #17 Pier #18
Sect. #1 8,290 11,606 11,606 9,948 11,606 9,948 11,606 12,435 12,435
Sect. #2 8,290 11,606 11,606 11,606 13,264 12,435 12,435 23,212 20,725
Sect. #3 11,606 16,580 13,264 12,435 13,264 27,357 16,580 33,160 33,160
Sect. #4 13,264 23,212 33,160 16,580 18,238 33,160 33,160    
Sect. #5 18,238 33,160   21,554 33,160        
Sect. #6 19,896     24,870          
Sect.#7 31,502     33,160          

  Analysis of Lifting, Driving and Ultimate Force

 

Factor of Safety

Location Lifting
Force, lb
Driving
Force, lb
Ultimate
Cap. - lb
Working
F.S.
Ultimate
F.S.
Pier #10 15,450 31,502 85,000 2.04 :1 5.50 : 1
Pier #11 15,450 33,160 85,000 2.15 : 1 5.50 : 1
Pier #12 14,420 33,160 85,000 2.30 : 1 5.89 : 1
Pier #13 14,420 33,160 85,000 2.20 : 1 5.89 : 1
Pier #14 14,420 33,160 85,000 2.20 : 1 5.89 : 1
Pier #15 12,875 33,160 85,000 2.58 : 1 6.60 : 1
Pier #16 12,875 33,160 85,000 2.58 : 1 6.60 : 1
Pier #17 12,875 33,160 85,000 2.58 : 1 6.60 : 1
Pier #18 12,875 33,160 85,000 2.58 : 1 6.60 : 1

Results

Location Approx.
Lift - in.
Depth to
Bearing
Pier #10 3-1/2" 24' - 6"
Pier #11 3" 17' - 6"
Pier #12 2" 14' - 0"
Pier #13 1-1/2" 24' - 6"
Pier #14 1" 17' - 6"
Pier #15 1/2" 14' - 0"
Pier #16 0" 14' - 0"
Pier #17 0" 10' - 6"
Pier #18 0" 10' - 6"

Slab Pier Installation Log

 
Slab Pier
Depth

Location and Installation Torque - ft-lbs

Pier A Pier B Pier C Pier D Pier E Pier F Pier G Pier H Pier J
5' 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500
10' 1,500 3,000 3,000 1,500 1,500 1,500 1,500 3,000 1,500
15' 3,000     3,000 3,000 3,000 3,000   3,000
 
Slab Pier
Depth

Location and Installation Torque - ft-lbs

Pier K Pier L Pier M Pier N Pier P Pier Q Pier R Pier S
5' 1,500 1,500 1,500 1,500 1,500 1,500 1,500 1,500
10' 3,000 1,500 1,500 1,500 3,000 1,500 1,500 1,500
15'   3,000 3,000 3,000   3,000 3,000 3,000

 

Results

Location Approx.
Lift - in.
Depth to
Torque
Pier A 0" 15'
Pier B 0" 10'
Pier C 0" 10'
Pier D 0" 15'
Pier E 0" 15'
Pier F 0" 15'
Pier G 0" 15'
Pier H 0" 10'
Pier J 0" 15'

Results

Location Approx.
Lift - in.
Depth to
Torque
Pier K 2" 10'
Pier L 2" 15'
Pier M 2" 15'
Pier N 2" 15'
Pier P 2" 10'
Pier Q 1" 15'
Pier R 0" 15'
Pier S 0" 15'

 

Pier Location Plan

 

Force
Lifting
14
Force
Driving
33
Capacity
Ultimate
85
Pier Installation Summary


Chance Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com