CASE STUDY GA110-1-9412

Atlas Piers Logo

 

SETTLEMENT OF
AN OFFICE
BUILDING BUILT
OVER LANDFILL

OFFICE BUILDING

Clarkston, Georgia


Engineered by:
Sailors Engineering, Inc.
Atlanta, Georgia

 

Installed by:
Atlas Piers of Atlanta
Alpharetta, Georgia

 

 

SETTLEMENT OF AN OFFICE BUILDING
BUILT OVER LANDFILL

OFFICE BUILDING
The building at the right is the subject of this report. The fill material and the major
settlement were found at this northeast corner.

THE PROBLEM!

Description of Site:

This two-story office building was built over a pit containing 10 to 12 feet of fill soil, wood, organics and other debris. Standard Penetration Test of the area revealed very loose soil. Blow counts in the area of settlement were on the order of one or two blows per foot per ASTM D-1586-67.

Description of Structure:

The building faces west and is of standard frame construction with a brick veneer resting upon a reinforced concrete slab. The exterior grade beam ranged from 4 to 5 feet tall in the area of the settlement. This suggests that the builder unsuccessfully attempted to reach suitable soil below the landfill pit. The interior floor was measured to have downward settlement of approximately 2-1/2 inches at the northeast corner. Large cracks were present in the masonry above the windows on the north wall and at the rear doorframe at the east side. (The photo on the previous page shows the northwest corner with a masonry fracture on the north side, and the view above shows the northeast corner.) Separations between the door and window framing and the masonry were also noted in the same areas. The interior showed significant distress in the walls on the second floor.

Special Techniques Required:

Each Atlas Pier Pipe Section within the area of fill had a 4-inch sleeve pipe installed over the Pier Pipe. The purpose of the modification sleeve was to provide enhanced stiffness and rigidity to the Pier, and to strengthen the segmented joints in the Pier Pipe.

PROJECT SUMMARY


Engineer: Sailors Engineering, Inc.
Repaired By: Atlas Piers of Atlanta,
Alpharetta, Georgia
Piers Required: Nine (9)
Part Number: AP2(PA)-3500.160M
Average Depth: Thirty-Nine Feet (39')
Amount of Lift: 1/2" to 2-1/2"
Driving Force: 75,500 lb. (Avg.)
Lifting Force: 32,445 lb. (Avg.)
Factor of Safety: 2.3:1 (Working Load)
2.8:1 (Ultimate Load)

Foundation Cross-Section Detail - Enlargement
The sketch above details the scope of the project and as-built configuration. At right are photos of the north wall showing the recovery achieved from the underpinning.

North wall

North wall showing the recovery achieved

 

SUCCESS!

Masonry separation

Recovery was nearly 100 percent

Detail of the masonry separation on the north side of the structure is shown above, note that after restoration the recovery was nearly 100 percent The recovery at the entrance on the east side of the structure was nearly perfect!

Masonry separation

The recovery at the entrance

The recovery at the entrance on the east side of the structure was nearly perfect!

 

Atlas Piers

INSTALLATION SUMMARY

Pier Installation Log

Location Lifting
Force,
pounds
Driving
Force,
pounds
Ultimate
Cap.,
pounds
Working
F.S.
Ultimate
F.S.
Pier #1 32,445 74,610 90,000 2.3 : 1 2.8 : 1
Pier #2 32,445 82,900 90,000 2.6 : 1 2.8 : 1
Pier #3 32,445 74,610 90,000 2.3 : 1 2.8 : 1
Pier #4 32,445 82,900 90,000 2.6 : 1 2.8 : 1
Pier #5 32,445 70,465 90,000 2.2 : 1 2.8 : 1
Pier #6 32,445 70,465 90,000 2.2 : 1 2.8 : 1
Pier #7 32,445 74,620 90,000 2.3 : 1 2.8 : 1
Pier #8 32,445 74,610 90,000 2.3 : 1 2.8 : 1
Pier #9 32,445 74,610 90,000 2.3 : 1 2.8 : 1

Results

Approx.
Lift
inches
Depth to
Bearing
feet
2" 47'
2" 33'
2-1/4" 36.5'
2-1/2" 36.5'
2-1/2" 40'
2" 40'
1" 40'
1/2" 40'
1/4" 39'

 

Analysis of Lifting, Driving and Ultimate Force

Foundation Restoration

Depth to Pier Bearing

THE Solution!  

   Atlas Piers

Chance Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com