Case Study 110-10
ATLAS RESISTANCE PIERS
Stabilize an Atlanta Retail Sports Store
Built Upon Uncompacted Fill!
Installed By:
Atlas Piers of Atlanta
Alpharetta, Georgia
UNCOMPACTED FILL CAUSES FOUNDATION
FAILURE ON SPORTS RETAILER!

This view shows the area of work, notice the large area
of fill soil. Fifty-seven ATLAS RESISTANCE PIERS were installed at the side, along
45 feet of the rear, and 30 feet at the front of the structure.
THE PROBLEM: This structure was built on a lot with a slope. After
the lot was leveled, the fill material under the structure began to consolidate. Soon the
structure began to show signs of distress, there was compaction of the fill. Cracks and
masonry misalignments appeared in the exterior walls.
Soil borings revealed that suitable bearing strata occurred at 40 to 45
feet. The engineers had another problem. There was a sewer line located 30 feet directly
below the footing. Drilling concrete piers would be impossible and relocating the sewer
line uneconomical.
| THE SOLUTION! ATLAS
RESISTANCE
PIERS |
 |
PROJECT SUMMARY |
| Installed
by: |
Atlas Piers of
Atlanta
Alpharetta, Georgia |
| Resistance
Piers: |
57 |
| Part Number: |
AP2S-3500 |
| Pier Depth: |
38 to 49 feet |
| Ave. Drive
Force: |
60,000 pounds |
| Lift Force: |
20,000 pounds |
| Ultimate
Capacity: |
85,000 pounds |
| Factor
of Safety: |
2.90 to 3.11:1
(working)
4.25:1 (ultimate) |
|
|
 |
The selection of ATLAS
RESISTANCE PIERS was the key to the success of this project. Not only did ATLAS
RESISTANCE PIERS provide superior structural support and allowed for quick completion;
it was the most cost effective solution because the sewer line under the structure was not
disturbed during the installation of the piers! Each ATLAS RESISTANCE PIER was
driven to a force greater than required to support the structure. The graph above shows
the average factor of safety on this project to be 3:1.
The photographs below show technicians installing piers.
