ATLAS RESISTANCE PIERS

CASE STUDY 110-12

 

Atlas Resistance Piers are Used
to Shore Existing Structure
Prior to Excavation

Alpharetta, Georgia

 

Installed by:
Atlas Piers of Atlanta
Alpharetta, Georgia

 

Designed by:
Parsons Infrastructure & Technology Group
Atlanta, Georgia

 

Support for Existing Structure
During Expansion!

View of the job site

This is a view of the job site where workers are finishing the new concrete floor. The ATLAS RESISTANCE PIERS provided support to the existing structure during excavation.

Description of Project: The existing structure houses the Bell South Central Office. Due to growth in the area, an addition to the structure was planned. The new structure has a finished floor elevation approximately 6’ - 8’ below the footings of the existing structure. The designer had to address the problem of supporting the existing structure while the soil was removed adjacent to the footing. Also, the owner needed to maintain operations in the existing structure without disruption from movements or vibrations during construction of the addition.

Description of Design: The engineers recommended support of the existing structure using ATLAS RESISTANCE PIERS. Suitable bearing for the piers was found at 59.5 feet below the existing footings. The concern was the strength of the exposed pier during excavation and construction. The stiffness of the pier was enhanced in this area by installing a pier sleeve over the 4 inch diameter pier pipe. The soil from below the existing structure was retained during the excavation by steel reinforced concrete retaining walls. This wall was constructed after each 18 inches of excavation.

Technicians installing the AP2P-4000M Atlas Resistance PiersTechnicians installing the AP2P-4000M Atlas Resistance Piers

Technicians are installing the AP2P-4000M Atlas Resistance Piers to the existing structure. The pier spacing was designed by the engineers to load each pier to 30,000 pounds.

Atlas Resistance Pier Summary

Design Engineer: Parsons Infrastructure & Technology Group, Atlanta, Georgia

Installed By: Atlas Piers of Atlanta -- Alpharetta, Georgia

Atlas Resistance Pier Product: AP2P-4000M -- ATLAS 2-PIECE MODIFIED
                                                                             RESISTANCE PIER

Number of Resistance Piers: 15

Average Drive Force: 60,000 pounds

Average Working Load: 30,000 pounds

Factor of Safety: 2 : 1 [100% above working load]

Average Depth: 59’ - 6"

 

Plan View

The plan view to the right shows the general layout of the 15 Atlas Resistance Piers on the structure.

 

Below is a cross sectional sketch of the Atlas Resistance Pier installed to the existing structure and the relationship of the new slab to the original structure.

 


 

Section

 

ATLAS RESISTANCE PIERS

After the ATLAS RESISTANCE PIERS are installed to the load bearing stratum, each pier is tested to a load of 60,000 pounds. Each pier then has 14 feet of 4-1/2 inch diameter sleeve installed over the pier. A working load of 30,000 pounds then applied to the pier and the pier pins are installed.

ATLAS RESISTANCE PIERS

After excavating approximately 18 inches of soil, steel reinforcing is installed and a wall is cast to retain the soil mass under the existing structure.

Completed shoring and support project

SUCCESS!

These photographs show the completed shoring and support project. The existing structure is fully supported and the soil mass under the structure has been retained. The floor slab for the new addition has just been cast.

 

Atlas Resistance Piers…

THE
SOLUTION!

 

 

Completed shoring and support project

Chance Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com