CASE STUDY IN227-2002-1
ATLAS PIERS

FAILED FOUNDATION THREATENS
ELECTRICAL POWER AT A UNIVERSITY!
Evansville, Indiana
Engineered by:
John F. W. Koch & Associates, Inc.
Evansville, Indiana
Installed by:
M-W Construction, Inc.
Evansville, Indiana
|
FAILED
FOUNDATION THREATENS
ELECTRICAL POWER AT A UNIVERSITY!

The engine and generator provide power to the university. The four foot
thick solid concrete foundation tipped and settled more than four inches! Two columns
supporting the upper level are visible. These also settled approximately 1-1/4 inches. Atlas Plate Piers were used to restore the columns.
DESCRIPTION:
The university generates power for operations with a 16 cylinder Ajax-Superior 2408
natural gas fired engine and electric generator. The engine-generator combination is
mounted directly to a solid concrete inertia block that measured 23 x 7 x 4 feet tall. The
plans called for one inch of Unisorb- I5-500-51 under the block and 1/2 inch of Unisorb on
the perimeter. Two steel columns that support piping and a deck for maintenance above the
generator had also settled up to 1-1/2 inches. These columns were supported off of
concrete spread footings adjacent to the generator inertia block. The combined weight of
the engine-generator and inertia block was calculated at 150,000 pounds!
THE PROBLEM:
There was a reported water line break near the Physical Plant prior to the settlement of
the inertia block, in addition water was seeping from the engine and piping. The engineers
concluded that water infiltrated the underlying soil and softened the bearing strata. The
vibrations from the generator agitated the wet clay and sandy soils further reducing the
load carrying capacity. In addition, inspection during restoration revealed that there was
no vibration absorption material under the block.
SITE CONDITIONS:
Soils testing at the generator revealed that there was water trapped above the clay in a
layer of pea gravel fill. Below the soil was brown and light gray clay with sand, soft and
wet. Approximately three feet below this clay was brown clayey sand, loose and wet. Due to
limited access, the boring was stopped at slightly over 7 feet. Another boring adjacent to
the building to a depth of 20 feet showed similar results. Standard Penetration Tests
revealed generally blow counts (N) in the range of 7.
PROJECT
SUMMARY |
ENGINE-GENERATOR RESTORATION |
|
Atlas Resistance Pier Product: |
AP2(PA)-3500.160M
2-Piece Modified Resistance Pier |
|
Number of
Resistance Piers: |
6 |
Average Depth: |
84 Feet |
|
Average Drive
Force: |
66.044 |
Average Lift
Force: |
36,050 lbs. |
|
Working Factor of
Safety: |
1.8 : 1
[Average Driving Force to Average Working Load] |
|
Ultimate Factor
of Safety: |
2.5 : 1
[Ultimate Pier Capacity to Average Working Load] |
|
Amount of Lift: |
2-7/16 to
4-9/16 inches |
|
PIPE SUPPORT PLATFORM RESTORATION |
|
Atlas Resistance Pier Product: |
AP2-PP(PA)-3500.160
2-Piece Resistance Plate Pier |
|
Number of
Resistance Piers: |
4 |
Average Depth: |
36 Feet |
|
Average Drive
Force: |
21.554 lbs. |
Average Lift
Force: |
12,613 lbs. |
|
Working Factor of
Safety: |
1.7 : 1
[Average Driving Force to Aerage Working Load] |
|
Ultimate Factor
of Safety: |
6.7 : 1
[Ultimate Pier Capacity to Average Working Load] |
|
Amount
of Lift: |
1-1/8 to 1-5/16 inches |
|
THE PLAN:
The Engineer specified Atlas 2-Piece
Modified Resistance Piers to be installed on each side of the inertia block.
Based upon the estimated weight of the unit at 150,000 pounds, the combined working loads
of the six modified piers would provide a design factor of safety of 2:1. The modified
pier is a good selection for this application because the pier has an added 4 inch
diameter Sleeve over the standard 3-1/2 inch Pier Pipe. The Sleeve stiffens the
segmented joints of the pier pipe and was specified to extend through the 7 feet of weak
and saturated soil found under the inertia block. The columns were to be restored using Atlas 2-Piece Plate Piers that were welded to the either
side of each column. The footing below each column was drilled to pass the Pier Pipe.
Following the lift, the engineer specified that the voids were to be filled with
structural grout.
The plan view at left shows the general layout of the engine-generator and how the Atlas 2-Piece Resistance Piers were positioned.
 |
THE INSTALLATION:
The Atlas 2-Piece Modified Resistance Piers
were positioned based upon the center of gravity of both the engine and generator so that
the piers would provide uniform lift and support. Each pier was carefully aligned
vertically prior to installation to suitable bearing.The square columns offered a
slightly different challenge. The engineer specified that two Atlas 2-Piece Plate Piers should be welded to each
column with a piece of plate steel installed on the two sides opposite the piers. This
would completely encase the column in the area of the Plate Piers and give adequate weld
length. The concrete footings below the columns were drilled to pass the Pier Pipe. During
the lift, the footings provided lateral support while the double pier design provided a
design factor of safety of 2:1.

|
The photographs
show technicians installing Atlas Piers using
quiet, vibration free hydraulic equipment. Each Pier was driven to a suitable bearing
stratum using portable equipment. The Inertia block or the column, footing and pipe
support platform was used as reaction to the driving force. The technicians carefully
record the driving forces at 3-1/2 foot intervals.
THE RESTORATION:
Restoration was performed in conjunction with others. First, the Plate Piers on the two
columns were lifted carefully and uniformly using 25 ton hydraulic rams connected to a
manifold and hand pump. The stresses on the pipes and electrical lines were closely
monitored during the lift.
The second phase of the restoration involved stopping the generator. The owner had
millwrights remove the supplemental shims and the grout that was installed to keep the
engine-generator level and in alignment when the inertia block settled and rotated. The
inertia block was then lifted using 25 ton hydraulic rams after the engine-generator was
resting directly on the inertia block.
Following the lift, structural grout was installed to fill the void created under the
inertia block and under the column footings. Finally, the openings in the service trench
were repaired.

The
hydraulic rams were installed between the temporary Lifting Head and the Atlas 2-Piece
Resistance Piers.
Once restored, the load was removed from the rams and transferred to the Atlas Piers.
The Lifting Heads and rams were then removed prior to filling the voids.

SUCCESS!
The inertia block and engine-generator were restored to level and raised to the
original "as-built" elevation. Actual load on the 6 the Atlas 2-Piece
Resistance Piers was measured at 216,000 pounds! The variation across the inertia
block was measured at less than 1/16 inch! The platform was restored to nearly "dead
level". The engine-generator was aligned, and the power was restored!
Atlas Piers |
INSTALLATION
SUMMARY |
Pier
Installation Log
| Location |
Lifting
Force,
pounds |
Driving
Force,
pounds |
Ultimate
Cap.,
pounds |
Working
F.S. |
Ultimate
F.S. |
| Pier #1 |
37,080 |
66,320 |
90,000 |
1.8 : 1 |
2.4 : 1 |
| Pier #2 |
37,080 |
66,320 |
90,000 |
1.8 : 1 |
2.4 : 1 |
| Pier
#3 |
31,930 |
64,662 |
90,000 |
2.0 : 1 |
2.8 : 1 |
| Pier #4 |
38,110 |
66,320 |
90,000 |
1.7
: 1 |
2.4 : 1 |
| Pier #5 |
36,050 |
66,320 |
90,000 |
1.8 : 1 |
2.5
: 1 |
| Pier
#6 |
36,050 |
66,320 |
90,000 |
1.8
: 1 |
2.5
: 1 |
| |
|
|
|
|
|
| Pier A |
17,510 |
28,186 |
85,000 |
1.6 : 1 |
4.6 : 1 |
| Pier
B |
17,510 |
31,502 |
85,000 |
1.6
: 1 |
4.6
: 1 |
| Pier C |
7,725 |
13,264 |
85,000 |
1.7
: 1 |
11.0 : 1 |
| Pier
D |
7,725 |
13,264 |
85,000 |
1.7 : 1 |
11.0
: 1 |
|
Results
Approx.
Lift
inches |
Depth to
Bearing
feet |
| 4-9/16" |
88'-3" |
| 4-1/16" |
74'-7" |
| 2-7/8" |
84'-2" |
| 2-3/16" |
84'-0" |
| 2-1/4" |
88'-3" |
| 2-7/16" |
84'-6" |
| |
|
| 1-5/16" |
36'-7' |
| 1-5/16" |
39'-9" |
| 1-1/8" |
33'-8" |
| 1-1/8" |
33'-8" |
|


|
|
|