 |
| Installing CHANCE® helical tieback anchors between Atlas Resistance® piers
|
Background Information:
The owner of an upscale home
embarked on a multi-million-dollar
renovation project. It included not
only normal remodeling but also
removing the indoor pool, building
a larger one and extending the
house to enclose it. A service facility
also was constructed under the
pool and its deck.
The bottom elevation of the old
pool was lowered and extended
farther under the house (which
included undercutting existing
bearing footings) to accommodate
a theatre room.
A 120-foot-long tunnel was
constructed from the house to a
detached garage.
Job Description:
The contractor learned early
not to undercut a footing. They
built a basement level room
adjacent to the extended front
entry, undercutting the footing.
The footing settled, cracking the
brickwork.
Kent Companies installed two
CHANCE® helical piles on the
foundation and lifted the area.
 |
| Adding an extension to a helical tieback anchor.
|
After that experience, the
contractor was much more
cautious. Renovations called for exposing the footing of the garage
during the tunnel construction. Kent Companies installed Atlas
Resistance® piers to stabilize the
footing, averting repetition of the
previous problem.
At the back area, two sections
of existing footings were to be
undercut by as much as 9 feet. This
construction required personnel to be working at the bottom of the 9-foot cut.
Shoring Design Plan:
The design of a shoring plan was overseen by Kent Companies, the concrete contractor, the owner and the site safety staff.
The shoring plan included:
- Installing 4”-diameter Atlas Resistance® piers
installed on 4-foot centers with required depths
more than 9 feet.
- Sleeving pier shafts with three sections to exceed
9 feet.
- Grouting the pier tubes.
- Installing a CHANCE® helical tieback between the
resistance piers and a 6"-wide steel channel waler to
add tieback stiffness to the resistance piers.
- Hand excavating behind the pier shafts and inserting
wood lagging as the excavation was extended to the
9-foot design depth.
 |
| Tieback anchor rods extended to steel walers for lateral support during basement wall construction
|
Rods were extended from the shoring tieback anchors
to provide lateral support required for the concrete
contractor during construction of new basement walls
in the area of the tiebacks.
The same procedure was followed as the excavation
process exposed three footing sections, including one
for an interior supporting foundation.
The result was "nothing happened" – no movement,
no injuries, no jeopardizing of man, machine or
structure.
Summary:
- 39 4”-diameter Atlas Resistance® piers were installed
to 38 feet for support.
- Three sleeves added per pier.
• Each pier was grouted.
- 38 CHANCE® 1½”-square shaft tieback anchors were
installed to 15 feet with threaded rod extensions
Adding an extension to a helical tieback anchor
as required to secure 6”-wide steel channel walers
and stabilize newly poured basement walls during
construction.
- 2" x 10" wood lagging inserted to shore the soil.
The project was a resounding success for Kent Companies.
|