COMPACTING FILL MATERIAL CAUSES
COLUMN AND SLAB FAILURE

 

Exterior of the job site

JOB SITE:

The photograph left shows exterior of the job site. The front structure is used for office space. The warehouse area behind the office also contained office space configured on two levels and supported by pipe columns off of concrete footings.

THE PROBLEM:

A leak in a drainage line under the slab caused localized failure of the slab in the warehouse and a column footing that supported an office above the warehouse. Soil tests revealed that the structure was constructed on uncompacted fill material containing organics and debris. Settlement occurred at the column when the moisture caused soil consolidation of nearly 5 inches!

THE SOLUTION:

The engineers proposed to install two Atlas Modified Plate Piers on opposite sides of the settled pipe column. The pipe column was mounted on a cylindrical concrete column cast upon a large rectangular reinforced concrete footing. The engineers decided not to disturb or attempt to raise the footing. The challenge was attach the Plate Piers to the round column and to drive the piers through holes in the concrete footing.

First, a section of channel steel was welded to the round column so that there would be flat surfaces to attach the framework that would hold the Atlas Modified Plate Piers. (See sketch on following page.) The Pier Pipe would penetrate the existing footing via holes cored through the concrete. The piers were each tested to loads exceeding 26,500 pounds. Then both of Atlas Modified Plate Piers lifted the column 4-1/2 inches with a force of 9,800 pounds on each. New mounting brackets were attached to the column flange and secured to the existing concrete footing column. The 4-1/2 inch void was filled with grout.

PROJECT SUMMARY

Engineered By:


General Contractor:


Ave. Driving Load:

Ave. Working Load:

Ultimate Capacity:

Structural Systems
Design, Inc.

Ayars & Ayars, Inc.
Omaha, Nebraska

27,350 pounds

9,785 pounds

90,000 pounds

Installed by:


Number of Piers:

Part Number:

Average Depth:

Factor of Safety:

Factor of Safety:

Great Planes Surfacing, Inc.
Omaha, Nebraska

2

AP-PP(PA)-3500M

30 feet

2.8 : 1 (Working to Driving)

9.2 : 1 (Working to Ultimate)

 

 Welder attaching the steel channel

Plan view of the pier placement

The sketch above shows a plan view of the pier placement. Steel channel was welded to the pipe column. The Atlas Piers were then mounted on structural rectangular tubing spaced away from the steel column so that the Plate Pier would clear the concrete cylinder below the column. The Plate Piers were installed and tested to an average force of 27,350 pounds. Then a lifting force was applied to both piers and the column was raised to the desired elevation.

The photograph above shows a welder attaching the steel channel to the round pipe column. The structure supporting the second floor office space is visible above the workers.

Pier Installation Summary

Welder installing the structural steel tubing

The photograph above shows a welder installing the structural steel tubing that was used to extend the Atlas Modified Plate Piers beyond the concrete column. The Atlas Piers were driven to a solid bearing strata approximately 30 feet below the grade level. After reaching solid bearing material 30 feet below the surface, each pier was load tested to over 26,500 pounds.

Technician installing the Atlas Pier

View of the Atlas Modified Plate Pier

The photo above shows the technician installing the Atlas Pier using quiet and vibration free hydraulic equipment.

Above right is a view of the Atlas Modified Plate Pier after the Pier Pipe had been driven to a verified bearing stratum. 25 ton hydraulic rams are positioned over the Top Pier Platform of each Atlas Pier. Then the column is lifted by applying equal pressure to each Pier.

SUCCESS!

The photo right shows how the column was restored to the proper elevation some 4-1/2 inches above the concrete. Steel legs were later welded to the base of the column to secure the column to the concrete. The void was filled with grout.

 

THE SOLUTION:
Atlas Piers!

The column was restored


Chance Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com