Case Study 578-3a
Mysterious Settlement of Historic
House Restored With Atlas Resistance Piers!
Milligan, Tennessee
Designed and Installed By:
REMBCO Engineering
Knoxville, Tennessee
MYSTERIOUS SETTLEMENT OF HISTORIC
HOUSE RESTORED WITH ATLAS RESISTANCE PIERS!
 Photo: Alan Broyles - Johnson City Press |
Description of
Structure: The structure is a kitchen wing addition to a 200 year old residence
located in eastern Tennessee. The addition was constructed in 1928. The footings and walls
are constructed of limestone and measure 18 inches thick. The hand hewn wooden beams
supporting the floor and rafters are attached with wooden pegs.
Distressed Observed: Settlement at the exterior wall opposite the
original structure was nearly three inches. Separations of the walls and roof at the
points of attachment to the original structure were nearly six inches. The gap at the
kitchen ceiling was so large that one could easily see the sky from inside the house.
Cause of the Problem: The exact cause of the settlement is still a
mystery. Some theories cite seismic activity or rock blasting at a nearby construction
project as possible causes. After nearly 70 years, the underlying soils became unstable
and lost compaction.
Repaired By:
Average Pier Load:
Ultimate Pier Capacity:
Number of Piers:
Amount of Lift: |
REMBCO Engineering, Inc.
Knoxville, Tennessee
40,250 pounds
85,000 pounds
10
2-3/4 inches |
| REMBCO
Engineering chose Atlas Resistance Piers as THE Solution for this
structure, which is listed in the National Register of Historic Places. Ten Atlas
2-Piece Piers were installed on three sides of the kitchen as shown on the plan shown
at right. The piers were driven to a suitable bearing stratum at an average depth of 32
feet. The average lifting force was 40,250 pounds. Restoration was nearly 100 per cent!
Only replacing trim molding inside and mortar replacement between the house and the
addition were required to complete the project. |

|

Photo: Alan Broyles - Johnson City Press |
SUCCESS!
The Atlas Pier Bracket is mounted below the footing and the pier is
gently installed to a suitable bearing stratum. Each Atlas Resistance Pier is
tested before the structure is lifted.
The photo at left shows a REMBCO Engineering technician at the
lifting control panel. The technician controls all ten jacks for a uniform and careful
restoration to as close to the original elevation as the construction permits. Once the
structure is restored, high strength pins are inserted into the Atlas Pier bracket
to maintain the desired elevation. Then the hydraulic lifting jacks are removed. |
THE Solution:
ATLAS RESISTANCE PIERS
PROJECT SUMMARY |
| Installed
by: REMBCO Engineering Knoxville, TN |
| Number of
Piers: 10 |
| Part
Numbers: AP2S-3500 |
| Avg. Pier
Depth: 32 feet |
| Avg. Pier
Load: 40,250 Pounds |
| Ultimate
Capacity: 85,000 Pounds |
The photograph below
shows a worker attaching the hydraulic line to the ram that will raise and restore the
structure. On this project, all hydraulic rams were connected through a control panel
where the technician monitors and controls the lift at each pier. This method insures even
and gentle support as the structure is restored. |
 |
Photo:
Alan Broyles - Johnson City Press
 |

The photo above
shows the structure in the settled condition, notice the large
separations at the roof, and where the addition joins the original structure.

After lifting the structure, the separations are nearly closed and the
floors restored.