Stair Tower at Quantico Marine Base
Restored With Atlas Piers

Quantico Marine Base
Overall view of the job site. The settled stair Tower is visible to the left of the original structure.

PROJECT SUMMARY


Engineer: U. S. Department of the Navy
Owner: U. S. Marine Corps Repaired By: Structural Solutions
Piers Required: Eight (8) Average Depth: Eight Feet (8')
Part Number: AP3(PA)-3500.160 Amount of Lift: 0" to 3/16"
Driving Force: 68,250 lb. (Avg.) Factor of Safety: 2.1:1 (Working Load)
Lifting Force: 32,702 lb. (Avg.) 2.4:1 (Ultimate Load)

THE PROBLEM:

Several years ago Stair Towers were added to the older structures at the Quantico Marine Base for emergency exits. In the case of Building 2007, the Stair Tower’s foundation was not situated on suitable soil to support the load. As a result, the foundation settled and the Stair Tower began to rotate away from the original structure. These photographs show the failing Stair Tower. Note the separation between the Stair Tower and the original structure at the fascia. Safety was also a concern as separations also occurred at the connections between the stair landings and Marshall Hall, the original structure.

The Failing Stair Tower

The Failing Stair Tower

These photographs show the failing Stair Tower. Note the separation between the Stair Tower and the original structure at the fascia. Safety was also a concern as separations also occurred at the connections between the stair landings and Marshall Hall, the original structure.

THE SOLUTION:

The Corps of Engineers specified Atlas Piers as the solution to the settlement. A Pier was specified at each corner nearest to Marshall Hall. These would serve as pivot points when the outer portion of the foundation was raised to the specified elevation. Six additional Atlas Piers were specified across the back of the Stair Tower and around the outer corners. The Piers were driven to firm bearing. Each pier was then tested and verified by a Department of the Navy inspector to at capacity of at least 65,000 pounds.

Technician is preparing the foundation

Above, a technician is preparing the foundation to accept the Atlas Piers. Note that the footing is notched to allow the piers to be mounted directly under the stem wall. The face and the bottom of the footing are carefully prepared prior to installation.

Technician is preparing the foundation

50-ton ram applying a test load After each pier was driven to a firm bearing stratum, the piers were load tested and verified by the U.S. Navy. The photograph above right shows a 50-ton ram applying a test load while the technician monitors the pressure gauge.

The Structure was lifted evenly and gently using a hand pump, manifold and a series of 25-ton hydraulic rams. One ram was mounted on each pier. The lifting force was monitored on a pressure gauge.

SUCCESS!

The Stair Tower was successfully lifted and rotated back to nearly the original position. Six of the Atlas Piers now carry a total working load of nearly 200,000 pounds.

Atlas Piers Logo

THE SOLUTION!
Atlas Piers

High Strength
Economical
Rapid Installation

The Plan

 

Atlas Piers

INSTALLATION SUMMARY

Pier Installation Log

Location Lifting
Force,
pounds
Driving
Force,
pounds
Ultimate
Cap.,
pounds
Working
F.S.
Ultimate
F.S.
Pier #1 32,702 65,000 80,000 2.0 : 1 2.4 : 1
Pier #2 32,702 66,000 80,000 2.0 : 1 2.4 : 1
Pier #3 32,702 70,000 80,000 2.1 : 1 2.4 : 1
Pier #4 32,702 70,000 80,000 2.1 : 1 2.4 : 1
Pier #5 32,702 65,000 80,000 2.1 : 1 2.4 : 1
Pier #6 32,702 78,000 80,000 2.4 : 1 2.4 : 1
Pier #7* N/A 66,000 80,000 N/A N/A
Pier #8* N/A 66,000 80,000 N/A N/A

Results

Approx.
Lift
inches
Depth to
Bearing
feet
3/16" 8'-4"
3/16" 8'-0"
3/16" 8'-8"
3/16" 7'-8"
2-1/4" 6'-10"
3/16" 8'-5"
0 5' - 6"
0 9' - 0"

 

Analysis of Liftin, Driving and Ultimate Force

 

Depth to Pier Bearing

 Chance Civil Construction
1026-B South Powell Road
Independence, MO 64056
Office: (816) 796-6800
Fax: (816) 796-0919
Toll Free: (877) 285-2739
Email: info@atlassys.com