
|
Determine the screw anchor spacing (SV, SH), screw anchor length and facing requirements for an excavation support system for a 23 foot deep excavation in a silty sand. The required design factor of safety for internal stability is 1.5, and for global stability is 1.3. Step 1 - Define Design Parameters Given: The unit weight and friction angle of the silty sand is 120 pcf and 30º respectively. The allowable bearing capacity of the silty sand at the bottom of the excavation is 4000 psf. The electrochemical properties of the silty sand are listed below:
A design live surcharge load of 100 psf is considered to be applied uniformly across the ground surface at the top of the wall. The wall face is vertical. Groundwater is located 60 feet below the ground surface. Chance Type SS5 screw anchors, for which lead sections and extensions are available in 5' and 7' lengths, are to be used for the screw anchors. The design life of the structure is one year. Design screw anchor lengths will be governed by the lead and extension pieces and thus will be 10', 12', 14', 15', 17', 19', etc. Step 2 - Check the Preliminary Feasibility of the SOIL SCREW® Retention Wall System The medium dense, silty sands at this site are well suited for the SOIL SCREW® Retention Wall System (i.e., good stand up time). The water table is well below the bottom of the excavation. The conditions at the site are therefore favorable for the SOIL SCREW® Retention Wall System. Design charts are used to determine preliminary screw anchor spacing and lengths for the given wall geometry, loading and soil conditions. For the soil conditions, f = 30o, enter the design chart (Figure A-2) along the x-axis at a wall height, H = 23 ft. A typical screw anchor spacing for soils with "good" stand up time is 5 ft. x 5 ft. Therefore, use the SVSH = 25 curve to determine the preliminary screw anchor length, L = 16 ft. (see Figure EX-1). Step 3 - Determine External Earth Pressures Use equation 3.1 to determine the earth pressure at the back of the reinforced soil mass.
Step 4 - Check Preliminary Screw Anchor Length with Respect to Sliding Available screw anchor lengths for Chance SS 5 anchors are 10', 12', 14', 15', 17', 19', etc. The 16 ft. preliminary length determined in Step 2 does not account for surcharge loading, which tends to increase screw anchor lengths. Try 19' screw anchors (length to height ratio of 0.83). For preliminary designs, for walls with the given soil and loading conditions, a length to height ratio of 0.8 to 1.0 is a starting point for the analysis and appears to be conservative. The horizontal force from the retained soil is determined using equation 3.5.
The horizontal force from the surcharge load is determined using equation 3.6.
Using 19' screw anchors installed at a 15º angle, the horizontal length, Lx, of the screw anchor is determined:
The factor of safety against sliding is determined as follows: Step 5 - Check Required Bearing Capacity at the Base of the Wall Determine the eccentricity (e) of the resultant vertical force (equation 3.9):
The vertical stress of the bottom of the wall is determined as follows (equation 3.10): Given the allowable bearing capacity is 4000 psf.
Step 6 - Determine the Allowable Screw Anchor Strength
The screw anchor wall is a temporary structure with a design life of one year. Using Table 3.5.2, the allowable design strength of the SS5 anchor is 45 kips. Step 7 - Estimate the Pullout Capacity of the Screw Anchors Determine the bearing capacity factor for helical anchors for a sand with an effective friction angle, f = 30o. From Figure 3.5.3, Nq = 14: Using equation 3.14, determine the pullout capacity of the screw anchors. Assumed vertical spacing is 5 feet (Step
2). Nail pattern is as shown.
The pullout capacity of the anchor at level 1 is determined as follows using equation 3.14: Screw anchors have 8-inch diameter helixes. The pullout capacities for the anchors at the various levels are determined as follows: y = 19sin15° = 4.9 ft. Step 8 - Define a Trial Facing System Try a 4 inch thick, 4000 psi shotcrete face with 6 x 6, W2.9 x W2.9 welded wire mesh reinforcing and 2- #4 vertical rebars at screw anchor locations. Try a screw anchor spacing of 5 feet vertically and horizontally and an 8" square by 3/4" thick bearing plate with a steel yield stress of 36 ksi. Step 9 - Determine the Allowable Flexural Strength of the Facing For typical soil nail wall construction practice, the facing is analyzed using vertical strips of width equal to the horizontal anchor spacing. For facing systems involving horizontal nail spacings that are larger than the vertical spacing or unit horizontal moment capacities that are less than the vertical unit moment capacities, horizontal strips of width equal to the vertical anchor spacing should be used. The area of steel for a vertical beam of width 5 feet (SH = 5 feet) with the anchor on the beam's centerline is determined as follows:
For a 5 foot wide vertical beam centered between the anchors, the #4 rebars are located at the beam edges and should be ignored. The area of steel is calculated as: The corresponding average nominal unit moment resistances are determined using equation 3.15 as shown below:
Step 10 - Determine the Maximum Screw Anchor Head Load that will produce the allowable moments determined in Step 9, using equation 3.16: Using Table 3.5.4, determine CF for temporary shotcrete facing 4 inches thick CF = 2.0 Step 11 - Determine the Allowable Punching Shear Strength of the Facing The punching shear strength is determined using equation 3.17:
Step 12 - Determine Critical Screw Anchor Head Load for Punching Step 13 - Construct Screw Anchor Strength Envelope Construct the strength envelope at each anchor level as shown below. At the wall face, the nail head flexural strength is less than the nail head punching strength and therefore controls. There are eight helices per anchor. Each step in strength equals the single-helix bearing capacity for the nail layer (Step 7). From the last helix (working from right to left) increase the pullout capacity in a stepwise fashion. If the pullout envelope working from the back of the nail does not intersect the flexural limit line, the strength envelope will look like that shown for Anchor 1. If the pullout envelope working from the back of the nail exceeds the flexural limit, then construct a pullout envelope working from the flexural limit at the head of the nail.
Step 14 - Evaluate Internal and Compound Stability. GoldNail 3.11, "A Stability Analysis Computer Program for Soil Nail Wall Design," developed by Golder & Associates, was used to perform the internal and compound stability analysis. The nail strength envelope developed in Step 13 needs to be modified for GoldNail. The increase in pullout capacity along the length of the nail is estimated for GoldNail as straight lines not step functions. An example of this modification for anchor level 2 is shown below: Within GoldNail there are several analysis options. The option used for this example is "Factor of Safety." Using this option, the internal Factor of Safety, FSinternal = 2.11 for the nail pattern defined in Step 7. See attached computer printout (Attachment EX1). The GoldNail output printout lists "Global Stability" not "Internal Stability." However, the location of the critical failure surface (circle no. 13) indicates an internal mode of failure, as shown on the GoldNail geometry printout
Step 15 - Check Global Stability Analysis performed for the given slope geometry by the computer program PCSTABL6H, developed by Purdue University and modified by Harald Van Aller, and the pre-processor STED, developed by Harald Van Aller. The resulting global Factor of Safety, FSglobal = 1.93. See attached computer printout (Attachment EX2). Step 16 - Check Cantilever at Top of Wall In Step 7 layout of anchor was assumed. The cantilever at the top of the wall from Step 7 is 3 feet. Using equation 3.20 check cantilever moment:
Check shear force at cantilever using equation 3.2.0:
Determine maximum allowable shear using equation 3.2.1:
|
|
|
||||